Make items lead time days from Item definition
Hi
I have Make items with Manufacturing lead time days entered directly on the item level, so that lead time computation not required to be run.
I would expect SO release work orders to consider these days to print start date from the schedule ship date of the order line. But it is not considering this, instead it takes only routing computed or making a random days.
Calendar is 5 and 2 days. Single shift 7 till 4 pm.
Not sure if am missing anything.
Regards
Viswa