Move Project from Workspaces
Hi Everyone.
I have a situation with a client and would like to share with you:
We know that there are some items to consider when we are going to move Projects (CBS, Resources, papers, calendar, costs and funds, user groups, etc.) but, in our client's environment, according to the guidelines received (attached), when testing some scenarios, we found some "inconsistencies".
Scenario 1:
Workspace (upper level) with CBS
Workspace (lower level) using the Workspace from upper level
Project using the CBS and filled all informations (budget, actual, fund).
When try to move the Workspace (workspace in same level), receive a message: