Is it possible to have WBS summary bars in calendar days while the activities show in working days?  See screenshot below:  Would love to have the summary bar indicate Calendar Days, basically calculating as "Finish Date" minus "Start Date" plus 1.  In the scenario below the Summary Bar would indicate 360 days and not 258 working days which is what's currently indicated.  It would be helpful to have this functionality.