Dear Srini and Arun,
Rebuildable process
1.We are Creating work order for Capital Asset which assigned with few transformer
2.Work order created
3.Released
4.Operation entered with Re-Buildable Asset Group(not with serials)
5.Only Asset Group entered with quantity (1)
6.After allocation we can issue any of the Re-buidable asset number with in the Asset Group
7.and child work order can be created to work with the replacement
correct me if am missing some steps in the above
and the question is the asset group is not allocated ,so we need to receive this asset group with number quantities or sugget me the rgt process