Primavera P6 Professional15.1 and ORacle 12 database
Dear Experts,
Require your help and guidance on this please
A user went to provide his Schedule Adherence based on his set baselines and they are missing. He can find his baselines in R011 but all later revisions are missing the baselines. R017 is the project he questioned the business admin earlier where his WBS was ok but his Activities went missing. How does something like this happen where baselines and activities go missing from a project. The user uses P6 client over WAN