Date_completed on WIP_DISCRETE_JOBS

edited Sep 24, 2020 9:13AM in Enterprise Asset Management - EBS (MOSC) 4 commentsAnswered

Hi Arun,

We are on 12.2.6, I've noticed that the date-completed on wip_discrete_jobs is the Actual Completion Date entered during completion and not the date the work order was completed (from eam_job_completion_txns).

For example, if I complete a work order today and enter the actual completion date as last month the date_completed on the wip_discrete_jobs will be the last month's date.

Is that a bug or intended behavior?

Thanks,

Gilad 

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center