Auto accounting setup in project costing
Hi Experts,
I would like to know how to configure auto accounting setup in project costing.
We have a requirement to capture the cost center automatically based on the project organization in iprocurement.
Hi,
You can configure Auto Accounting using below Setup
Navigate to Projects Responsibility ---> Setup ---> Auto Accounting
In this you have to define Rules for each Segment
For defining Rules you are can use 3 methods :
1. Constant
2. Parameter
3. SQL based
After you define the rules , Navigate to Projects Responsibility ---> Setup ---> Auto Accounting ---> Assign Rules
To assign above defined rules to each segment.
This auto accounting gets called in Projects whenever you run Distribute process, Interface transactions to GL or for any adjustment transactions done in PA.