Tips & Techniques: Regularize unconventional practice on shop floor
You may refer to entire list of Tips & Techniques documents at :
Your feedback makes the content more refined.This document will be updated on regular basis as per the new learning.
Situation
The customer maintains heavy equipment. During the maintenance there is an unconventional practice of pulling the components of other machine which is also under maintenance to complete the maintenance of a priority machine. The technician was going to stores later, and getting spare components for the low priority machine. And the material issued against the lower priority machine, included the components which were pulled for maintaining the other machine.