Resetting a meter reading after replacing one rebuildable by another
I need help
we want to use PM scheduling based on meter reading in EAM
We are receiving a data from an external database once a day
If I define a meter associated to rebuildable asset (serial)
During one-step material issue one rebuildable asset (serial) replaced by Another
Is there a way to automate the process that a meter for new rebuildable asset will reset automatically also the meter will be associated to a new asset ?
thank you
This is not a standard feature. You need to use a custom procedure that can be called and meter associated.
Regards
Srini