daily Bucketed forecast-Planned order problem
Hi all,
ACSP with OPM enabled org
I have a daily forecast for a specific item say for example 1 TON / DAY.
The planning engine should be generating a planned order with the 1 TON each day, but this is not happening, its generating a planned order day after the other.
for example
Forecast
2 OCT 2020 1 TON
3 OCT 2020 1 TON
4 OCT 2020 1 TON
5 OCT 2020 1 TON
6 OCT 2020 1 TON
Planned order (as the planning engine generates it)
2 OCT 2020 1 TON
4 OCT 2020 1 TON
6 OCT 2020 1 TON
Ignoring 3 and 6 ..what could be missing ?