F3112 operation sequence scheduling
Hi all,
I have a question regarding operation sequence scheduling in work order routings.
Currently there is a one day difference between the due date of the last routing step and the requested date from work order header. For example if the requested date (F4801.WADRQJ) of the order header is 02.09. the due date of the last routing step (F3112.WLDRQJ) is scheduled for 01.09.
If I should guess, I would say this is something like shipment preparation time. But I have no idea there to maintain that. We would like to get rid of that.
I would be very grateful if someone could tell me where this can be set.