Hi,

I have one custom work flow having a "Halt" task added to it. But after the expiry time the workflow is not resumed so as per the guidelines if one manually trigger the "Escalation Monitor Batch" using Work flow operations tab in Workflow design aid it is triggering back. So inorder to avoid this manual step how this has to be scheduled?

The issue is not happening in DV but in other environments happening. How to troubleshoot this any leads please


Recently customer went on tool update to 9.2.4.3.


Thanks,

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center