JDE E1 Mid Month Go Live Feedback Inquiry
Our customer in Canada, is rolling out JDE 9.2 to their Canada locations. They are already live in a pilot site in Canada and Europe, as well as in 7 locations in the US. So far all their cutovers have been at the beginning of the month, following the month end close in the legacy system.
This time around, they were scheduled to go-live on Nov 30, right after closing the month end in the legacy system, however due to some outstanding issues they need to push out their go-live by 2 weeks. They have asked us to share experience, in terms of how this would impact them from the go-live cutover and month end perspective, what additional activities would they need to consider, and what are the risks besides the fact that they are going live in December which is also quarter end and year end, which they are already aware of, however they are