Hi,

I'm looking for a solution similar to 'spread forecast evenly' option in ASCP, but based on supplies.

Example:

There's demand for 500pcs of item A in January, 800pcs in February and 1300pcs in March. In total 2600pcs.

Jan + Feb + Mar = 13 weeks

Average weekly demand= 200pcs

ASCP will plan supplies accordingly to demands - 500pcs in Jan, 800pcs in Feb and 1300pcs in Mar.

I would like to plan 200pcs of item A each week. Does anyone have any idea of how to do it in unconstrained plan?