How does PO Promise date affect the ASCP planning process
Our procurement department is struggling to keep up with the revision incrementing on a PO when the promise date is updated. They are updating the promise date when a vendor provides an updated delivery date because the belief is that the ASCP planning process needs the correct dock date to plan.
Are we misusing the promise date field?
Does ASCP actually peg supplies according to the promise date or is this not used in pegging calculation?