Hi,
Currently we have the lead times for OSP item/process is setup as 1 day and when i create a discrete job, i see that the start dates and completion dates for OSP operation are same day because of the lead time setup. In actual, when we send out the items to vendor for OSP processing, it might take 2-3weeks. I need your inputs on, how to adjust the lead times to fix this issue. Is it at the item level or need to adjust resource scheduling? Any inputs on this is highly appreciated, thanks so much. We are on EBS