WBS copy & paste including activities
When I copy & paste a WBS element including the activities P6 pastes the new WBS with the activities numbered in the order of entry and not by the numbering of the activity ID.
In below example I copy WBS Code TEST.1 to TEST.2.
A1005 Test Activity is the second activity before the paste, but the third activity after the paste.
Is there any way to execute the copy & paste, so P6 pastes the new WBS and activities by the original Activity ID numbering?
--Steve