Publishing a Workplan Gives Error "A Required Cost Rate Is Missing". (Doc ID 2009150.1)
Hi
I have Cost and/or Conversion Rates are missing for some planning resources. The summary amounts may not be correct.
I have followed the document
Publishing a Workplan Gives Error "A Required Cost Rate Is Missing". (Doc ID 2009150.1)
The SQL Gives the Resource name for which
pa_budget_lines.cost_rejection_code = 'PA_FCST_NO_COST_RATE'
However, when I check the Organization Labor Csotig Rule for the Operating unit, the cost rate schedule used ( employee cost rate schedule ) has got Cost Rates Defined for this Employee Resources for the Operating Unit.
I have checked exchange Rates and the exchange rate exist....