Hello,
Trying to create a change request with the expectation that existing PO will be updated (change order) but it does not happen. Instead, a new PO is created.
Is it working as designed? Or am missing some config/step?
Here are the replication steps:
1 Create ePro Requisition with one line
2 Approve and Source to a PO
3 Create a Change Request by adding one more Req line
4 Approve the Req
5 Approve Change Request and Process Change Order
6 PO Change Order created for existing line (if changed) and NO new line added to the PO
7 Expedite Req/Quick Source process creates a New PO for the new line