How to assign one task to many P6 Team Member users to update the progress.
The above requirement should be achieved using Global activity codes for certain activities which need an update from Team Member users.
Assigning Activity Owner or Primavera Resource to activity makes one user update one task.
whereas am looking at one task that should update by many users.
We have P6 EPPM 15.1 Version.
Please advise how to achieve this.
Thanks & Best Regards,
Sheik