EAM- Is it possible to capture the original scheduled start & end date before the planner updates?
Hello,
Our business wants to compare the original scheduled start & end dates of a WO when released and the updated scheduled start and end dates when a planner at the plant updates the schedule?
To elaborate on the above ask. Monthly PM WO is released to the plant with the system generated scheduled start & end dates. Planner updates the scheduled start & end. Unfortunately, Oracle don't keep track of the scheduled dates history. Therefore the original scheduled start & end dates is overwritten with the new dates. Our business wants to review why the plant (we've 40+ plants) didn't act as per the system scheduled start & end dates? Our current WO history suggests actual start & end dates is aligned with the scheduled start & end dates.. in reality it is not