Mark up Percent for Non Labor resource
In the Rate schedule for Non Labor resource i have setup 5% , also setup costing rate and attached to Labor costing rule for Employee and attached the costing rate schedule and Non labor resource markup rate schedule at Project type setup. I have entered pre approved batch for usage expenditure type class for an employee, i ran the PRC : Distribute usage and Misc cost program and ran the PRC : Generate cost accounting events for usage cost but system is not picking up costing rate and showing entered hours only
Please advise why system is not picking up Employee rate
Thanks