Requsition is completing during the REQ Close process on the same day it was entered.

edited May 12, 2021 5:12PM in Supply Chain Management - PSFT (MOSC) 2 commentsAnswered

Some users are entering requisitions and on the same day as the entry, after all approvals are complete, the requisition is closing the same day when the REQ Close process is run that night. The requisition has no time to be processed into a PO or placed on an RFQ.