PSI and None Time Phased Budget

in Projects - EBS (MOSC) 1 commentAnswered ✓

We are using Cost budgets which are Not Time Phased.

When we run project summarization: PRC: Update Project Summary Amounts for a Single Project, our Project Status Inquiry ITD - Cost Bgt column shows Total Budget / Total # of PA periods from STart/end of task.

so for example:

Budget = 1000

Project Duration = 4 PA periods

Accumulate during first period, ITD Cost Bgt = 250.00

Is this what others see in your instance, I just don't recall seeing the accumulation spread across periods when the Time Phased By = None in the Budget Entry Method.

Thanks in advance.

ER