PSI and None Time Phased Budget
We are using Cost budgets which are Not Time Phased.
When we run project summarization: PRC: Update Project Summary Amounts for a Single Project, our Project Status Inquiry ITD - Cost Bgt column shows Total Budget / Total # of PA periods from STart/end of task.
so for example:
Budget = 1000
Project Duration = 4 PA periods
Accumulate during first period, ITD Cost Bgt = 250.00
Is this what others see in your instance, I just don't recall seeing the accumulation spread across periods when the Time Phased By = None in the Budget Entry Method.
Thanks in advance.
ER