How to get item shortages listing of Oracle R12 ATP Availability to expedite promise date
Need a detailed supply-demand profile of component shortages for single ATO assembly or for a sales order with multiple ATO assemblies. Oracle R12 ATP Availability Functionality provides a promise date for an assembly or by sale order line but the requirement is to expedite component shortages to meet customer request date.
We view numerous shortages with material constraint dates in the ATP pegging pane following ATO item configuration structure of each sales order line from ATP Detail window pegging pane but unable to find any consolidated listing of material shortages causing delays by item/period to meet the customer request date. Is there any standard or custom functionality that caters to this or any known solution approach followed at any business implementation? Appreciate to receive any other viable suggestions also to resolve this issue.