Creating a 3-Week Look Ahead Report
The filter in the schedule / activities window allows the use of <= DataDate + 3Weeks but the Report area does not have that functionality.
Has anyone discovered a work around?
I tried creating an Activity configured field formula that would identify activities with start dates <= Project_dataDate + 3W (using plusWeeks). Unfortunately the Activity formulas do not recognize Project fields.