E1 34 Item branch additional system info questions
Hi everyone
We are setting up the requirements planning system and I would like some advice in regards item branch parameters.
We have following escenario
We have following escenario
• Two manufacturing plants call A y B, they send production to E.
• Two warehouses where the procurement process happens C and D, both send items to A, B or F
• One distribution center where sales orders and forecast exist called E
• One warehouse "F" which is used to stock inventory due to capacity constrains, this warehouse receives from C and D, and send items to A and B.
My questions are in relation to the planning code and planning fence rule: