Kit component lines Dates are out of synch with parent if Preference is used

I am on JDE Oneworld 9.2, just noticed this today in both P4210 and P42101.

If you set up a kit, let's say just one component. You enter the kit, confirm the Kit Selection window, in the P4210 or P42101 grid, change the scheduled pick date to say 9/1/21, promised ship = 9/2/21, and promised delivery = 9/3/21, then confirm the Kit Selection window again. Re-inquire on the order, you will notice:

  1. If the P4210 version pro-opt says "Preference profile processing = 1" on the Preference tab, the date changes on the parent were not pushed to the child.
  2. However, if Preference profile processing = blank, all dates are in sync between the parent and the child.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center