I am on JDE Oneworld 9.2, just noticed this today in both P4210 and P42101.
If you set up a kit, let's say just one component. You enter the kit, confirm the Kit Selection window, in the P4210 or P42101 grid, change the scheduled pick date to say 9/1/21, promised ship = 9/2/21, and promised delivery = 9/3/21, then confirm the Kit Selection window again. Re-inquire on the order, you will notice:
- If the P4210 version pro-opt says "Preference profile processing = 1" on the Preference tab, the date changes on the parent were not pushed to the child.
- However, if Preference profile processing = blank, all dates are in sync between the parent and the child.