Not able to create Requisition from Project contract
I have setup Supplier contract(subcontract) in Project contract module , in DTS i have specified all the relevant details , Project number, Task, Expenditure type , date, Expenditure Org , supplier details etc and checked the flag 'Procure to Pay' flag, i have linked customer contract to this supplier contract and initiated the Requisition for this Supplier contract LINE but when trying to run Requisition import not able find Import source 'OKE' in parameter
Please assist if any process steps or setups are missing??