Team,
We have an issue where ATP Inquiry not considering the specific IR's where the need by date falls within the infinite time fence defined in the ATP rule.
ATP Rule with 100 days as Infinite time fence days
IR#233 with need date 12-JUL-2021
IR#254 with need date 12-Oct-2021
In the above scenario, only IR#233 is considered but not IR#254.
Please let me know if you have valid reason for the above case.
Regards,
Siva