How should I set up a resource costs

edited Jul 9, 2021 10:26PM in Primavera (MOSC) 4 commentsAnswered ✓

I am using P6 stand alone version 19. How do I set up a resource when I have the following known quantities: a) Resource ID, b) budgeted units (10/d) of resource, c) cost/hr of resource ($100/h). I did an example resource but I get $0.00 for budgeted cost. Can P6 calculate what the budgeted cost would be if I have the above known quantities?