MRP Schedule Interface Not processed by Planning Manager
Hello
I am trying to load the data from legacy to create MDS entries into Oracle. I have inserted the following fields into MRP Schedule Interface, however planning manager is not processing the records. Any help is appreciated.
SCHEDULE_DESIGNATOR, ORGANIZATION_ID, INVENTORY_ITEM_ID, SCHEDULE_DATE, SCHEDULE_QUANTITY, Process_Status as '2', Source_code)
Oracle version R12.2.
MRP Schedule interface load program is not spawned by Planning Manager. Both Schedule interface load and MRP relief worker program is enabled in the instance.
Regards, Viswa