Opening a P6 file created by another user
When I open a P6, file created by a colleague, some of the task durations are much greater (eg. 90 days instead of 2 in some instances) than what she has inputted. Can anybody help/ direct me as to whether there are some settings in my copy of the software which may be distorting these durations? I am using P6 Professional 19.