P6 Professional 19.12 Resource Assignment Price/Unit Imports as $1.00/h^

edited Sep 23, 2021 9:06PM in Primavera (MOSC) 1 comment
My ASST SCN has a payrate of $39.62/h as displayed below.


I export the below schedule with the respective activity resource assignments.


The exported TASKRSRC worksheet displays as below.


I import this to a schedule with no resource assignments.

When the Resources and Resource Assignments are imported I get the below.


Why does the Price/Unit import as $1.00/h^?

I cannot manually change the Price/Unit of Assisstant Scienctist/A.

The only way to correct the Price/Unit is to delete the resource assignment and re-assign the resource. But this erases the advantage of importing the Resource Assignment from Excel.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center