Can you import a schedule from 15.1 to 20.12?
The schedule was built and maintained in 15.1 then they set up a new data base with 20.12 and imported the XER into 20.12
The schedule loses actualized dates every time the data date is updated
Is there a solution to this issue? or do we have to start over ?