AP Invoice linked to Project - Expenditure Item Date for reversed Item line different to Tax line?
We have this scenario, using R12.1.3:
- Raise REQ in October, linked to Project with Expenditure Item Date of 31-DEC-2021
- REQ approved, converted to PO
- AP Invoice matched to PO, Item and Tax Distributions have Expenditure Item Dates also of 31-DEC-2021
- Validate and Account AP invoice.
- PRC: Interface Supplier Costs runs and Expenditure Items created against the Project
- Back in AP, user Discards Invoice Line
- User matches invoice to PO again, but this time, changes Expenditure Item Date on Item Distribution to today's date of 08-OCT-2021, instead of it being 31-DEC-2021.
- Validate and Account AP invoice.
- PRC: Interface Supplier Costs runs and Expenditure Items created against the Project