When Importing OPC to P6, EV changes to Zero Values and now it wont calculate in P6
I have the project open in OPC, the EV calculates just fine. Then I export to XML and bring in into P6. The values are now Zero and after trying everything, the activities will not calculate out to anything other than Zero. (and yes I am pointing the same baseline in both applications) Please help before I have to write a ticket.
for Oracle's Eyes.... Not sure it this should be in the OPC or P6 Forum.