When do planned orders get firmed
Hi, I am trying to create a Simulation plan.
All my parts are MPS planned ( barring very few)
Objective is
1. Create a exact replica MPS called simulation MPS ( In terms of plan options) of the Actual Production plan.
2. Add a manual MDS in the org where user can play /simulate the demand
3.Feed the PROD MPS in the Demand schedule tab , so as to get the PROD MPS data.
The problem is all the planned orders ( which are firmed and not firmed) are coming as firmed in the simulation plan .
Therefore I think the pegging is giving priority to al these planned orders and dedeating the purpose of my simulation plan.