Questions about Upgrading P6 EPPM 18.8.20 to latest 20.12 version
Current set up is 18.8.20 on Windows 2012 servers. Current DB is Oracle 12C.
We want to upgrade the Application servers to Windows 2019 and the Database version to 19C.
Can I upgrade the application servers from Windows 2012 to Windows 2019 or do I need to do a fresh installation on the Windows 2019 servers?
On the database, can I do the database upgrade on the current server, or do I need to do a fresh installation on the Oracle 19c DB server?
I have patched my system in the past, but I have not done a FULL version upgrade. Does anyone have any good information for me to help me out?