LOE activities and changing Budgeted Units/Time - P6 Version 20.12
I have several LOE activities in our schedule. These LOE activities in the management portion of our WBS are resource loaded with management personnel/resources and the idea is that we would like them to capture a percentage of the management’s time in between the two activities it is supporting. The activity is linked from 1 milestone to another milestone in the schedule SS and FF. The problem is that for example: The resource’s budgeted units/time is not staying the same we want it to. It is changing. We would like for it to stay the same amount of hours/day and recalculate the budgeted cost. Instead, the