Updating a Baseline
I have a service request open on this but thought it beneficial to throw it out to the community. I have an issue when trying to update a baseline. Update fails with what look like runtime errors in a window I can't do anything with. P6 bombs out and I have to kill it. Some facts:
Current Schedule: Data Date = 11.1.21. Last modified date = 11.9.21
Baseline Schedule: Data Date = 7.14.21. Last modified date = 9.27.21.
I tried updating both with "Ignore last data date" checked and without. Same result.
Anyone else have this issue?