Planned orders for Phantom BOM in ASCP
•A make item is setup as Supply Type ‘Phantom’
This allows the item to be ‘Phantom’ when it is called out on other BOM’s
•This make item can also be ordered directly on a Sales Order
In this case, it is collected by ASCP and a Planned Order is suggested
However, the Planned Order has an action of ‘None’ and is unable to release to create a work order
In order to release the work order from plan workbench, the item master supply type has to be changed to ‘Push’, then changed back to ‘Phantom’
Is there a different approach which can be taken to maintain the ‘Phantom’ when called out on BOM’s, but also allow a work order to be released when ordered directly on a Sales Order?