WO Header Start Date Earlier than WO Routing Start Date

JDE E1 9.2

Can system be setup so that R31410 runs and results in WO Routing Start matching WO Header Start when WO Header Start is earlier than variable lead time would otherwise calculate?

For example, in normal operation we create WO header with Request Date = 1/7/22. Item's variable lead time results in WO Start Date = 1/6/22 for this item. We run R31410 to Attach Parts List and Routing resulting in WO Routing Start Date = 1/6/2022 matching WO Header.

Sometimes want to manually set WO Start Date earlier to prioritize an order over other orders while keeping customer's Request Date. Create WO for same item with Request Date = 1/7/22, but manually input Start Date = 12/30/21.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center