Performance % Complete Not Calculating
I have a project that is in progress and does not calculate performance % complete until the activity is complete. The admin settings are set as performance % complete equals activity % complete. The activities have progress and show percentages in activity % complete.
Performance % complete and Earned Value Cost are both blank. A baseline is assigned.
Activities are task dependent, fixed duration & units, and physical % complete. Resources and cost are assigned.
Thank you.