Completion of Successor Activity before the Predecessor activity
the end user / P6 pro doesnt have option to control the progress update on successor activity(especially FF/FS relationship) without completion of predecessor activity.
If users would like to complete successor activity without complete predecessor activity,is there any options that gives this flexibility to control the behaviour - avoid the successor activity completion before predecessor? Constraints option doesnt help.