We are in 9.2 and setting up the MRP system to help with inventory ordering for equipment maintenance items. I read in the MRP set up documentation that a "generic" branch plant of ALL could be set up in lieu of individual branch plants. This does not seem to work. I can get information in P3411 for branch plants that have work day calendars set up for them specifically but I get Date Generate Failed if I try to process R3482 on a branch that does not have a specific calendar.

Any ideas would be greatly appreciated!

Thanks!

Angelina