Outside Operations Order created from R31410 is not creating as per lead time

For example, if there are two routings in a WO that are Outside Operations and one of them (routing 10) has a lead time of 2 days and other (routing 20) has 3 days lead time and requested date is 5/20:

routing 10 outside order should have start date 5/15 and due date 5/17

routing 20 outside order should have start date 5/17 and due date 5/20

instead both have 5/15 start date and 5/20 due date