Fusion PPM - Query/Report on Project Task Percent Complete
Current Release: Oracle Fusion Project Portfolio Management - 22A
Our project managers update project tasks' Percent Complete through Project Management / Manage Project Plan page. I have not seen this field available in OTBI in any of the relevant subject areas.
I created a BI publisher report for Project Status reporting and am having problems selecting the current Percentage Complete field (users update the field many time through the course of the project).
The only table/field I found is: PJT_PROJ_PLAN_LINES.Percent_Complete
Any suggestions for only pulling the current (latest) Percent_Complete value into a query?
Thanks