Multi Facility planning Availability Check for Maximum Reorder Quantity

Hi,

We configured system to use multi facility planning along with Maximum reorder quantity, When the available check is ON in P3403T (Branch Plant Relationship) system is creating messages only based on the multiple reorder quantity and ignoring the remaining demand

eg: demand for July 1st is 1000 and if the maximum reorder quantity is 600 system is creating OT message for 600 and ignoring the remaining 400 quantity when the availability check is ON in Branch plant relationship. Test result attached with screenshots for the analysis