How Co/By Ratio is Determined When Planning a Process in MRP
When setting up a Process in MRP, the amount of Co/By Product is determined by the values on the Coproduct Row exit from the Routing step. The Routing step has Effective From and Thru dates. When a Routing Step with one set of Co/By Products is "expired" and a new Routing step has new Co/By Quantities (or Items) effective for a given date range. These dates produce the desired results in Capacity Planning but not in MRP (R3482/R3483). This new KM document explains how planned output of a Process is determined in MRP. Doc ID 2867407.1. https://bit.ly/3yJ79fD